The Town of Sullivan's Island has partnered with Everbridge to bring you up-to-date alerts from the Town of Sullivan's Island. Registration is free and you will be alerted via text message and/or email. Click here to sign up today!  NOTE:  Please check with your cell phone provider for fees to receive text messages. 

 

Breach Inlet has restricted access due to the current sand refurbishment project.

Stormwater Outfall Improvements Station 19 & 25 (SCEMD 4492 COVID-19)

The Town of Sullivan's Island proposes to complete the design and implementation of the stormwater drainage outfalls improvements at Station 18.5 Street and Station 25 Street because of high-volume coastal flooding and rainfall events. The Town will complete Phase 1 of the project, which consists of the non-construction activities necessary to plan, survey, engineer, design and permit the proposed project. 

Phase 1 Deliverables should include:

  • Final Engineering and design documents for the proposed activity demonstrating eligibility with HMA guidance.
  • Updated cost estimate based on final design.
  • Revised work schedule to implement the proposed measure within the remaining grant period of performance. 
  • Updated Benefit Cost Analysis (BCA) demonstrating the final proposed project to still be cost effective is required. 
  • Ground disturbance information, including area and depth of proposed ground disturbance. Maps of proposed ground disturbance should be provided. Phase II may require consultation by FEMA with SHPO and tribes.